Cost headings
(Bill of Materials, Estimating, Works Orders)
When calculating the cost of BOM A stock assembly and process costing system, which provides facilities to specify the structure of finished items in terms of sub-assemblies and components.s, estimates Forecast project costs, based on expected costs of labour, machinery and operation times. In Manufacturing, estimates are produced for one-off items or non-repetitive batches. or works order The authority to produce a part using the components specified on a BOM and the process specified on the routing.s, the values are accumulated in a cost heading.
Use this window to set up your cost headings. Five cost headings are supplied by default:
- Labour.
- Machine.
- Materials.
- Subcontract.
- Tooling.
Cost headings are associated with cost elements in the following way and the most appropriate cost type is applied automatically:
Cost Heading |
Cost Elements |
Where |
Cost Type |
---|---|---|---|
Labour |
Labour Resources |
Labour Resource Record Labour Resource Group Record |
Labour |
Machine |
Machine Resources |
Machine Resource Record Machine Resource Group Record |
Machine |
Materials |
Stock Items |
Stock Item Record Product Group |
Materials |
Subcontract |
Operations where the Subcontract check box is selected. |
Operation Record |
Subcontract |
Tooling |
Tool Resources |
Tool Resource Record Tool Resource Group Record |
Tooling |
Associating cost headings with cost heading types allows you to group cost headings and amalgamate costs during reporting.
You cannot associate a cost heading of type Materials with:
- Labour Resources.
- Labour Resource Groups.
- Machine Resources.
- Machine Resource Groups.
- Tool Resources.
- Tool Resource Groups.
- Operations.
You cannot associate a cost heading of any type, other than Materials, with a stock item or product group.
To do this, you must set up your own cost heading, such as Tooling Materials, and associate this with a stock item in the Stock Item Manufacturing tab.
You must have:
- Created nominal accounts to select for your cost headings in the Nominal Ledger.
To maintain cost headings
Open: Manufacturing System Manager > Settings > Cost Headings.
- To add user defined cost headings, click Add and enter the Name of the cost heading.
- For each user defined cost heading, select the Type.
- For each cost Name, enter the following default information.
- To delete user defined cost headings, select the cost heading and click Delete.
- Click Save.
You can amend the Overhead Recovery %, Nominal Account and Overhead Nominal Account default settings for individual resources on the resource record.
Note: You cannot delete the standard cost headings.