Conversion (EST settings)
Open: Estimating > Utilities > System Set Up > Estimate Settings | Conversion.
Enter the following setting:
-
Primary Constraint
When you convert an estimate to a BOM, you can determine whether labour or machines are to be used as the primary resource within BOM following the conversion. If you select Labour then the labour cost is used. If you select Machine, then the machine cost is used.