Confirming build (BOM)

Note: If you have not reserved specific stock components by allocating stock, use the Build routine to allocate and build immediately.

To build from allocation

Open: Bill of Materials > Processing > Confirm Build.

  1. Select the Allocation No from the drop-down list.

    The Allocation Reference and Date are displayed automatically.

    The Build Details area of the window lists the BOMs that have been allocated and are waiting to be built.

  2. To view a list of the components in the allocation and the settings used when the allocation was created, click View Allocation.
  3. Enter the Build Details.

    • The Build Date is associated with stock and nominal postings. It defaults to today's date but you can choose another date if required.
    • Enter a Build Reference.
    • For each Stock Code item:
      • If you are using version control, confirm the version that is to be built.

        Note: You can only build the current active version.

      • If you are using multiple locations, select the Warehouse and Bin locations.
      • Enter the Qty to Build.

        Note: You cannot increase the quantity of a finished item above the outstanding quantity for the item on the allocation. You can build less and either undo the allocation for the remainder or come back and complete the build later.

        The quantities will include the scrap percentage if you have selected to calculate scrap in Build or Allocation on the BOM Settings Scrap tab.

  4. If Print Build Report was selected, the Build Report appears.

    • Click Close to complete the Confirm Build process.