Post timesheets to Project Accounting
Use this if you have chosen to manually post timesheets to Project Accounting.
When timesheets are posted to Project Accounting, a single project transaction record is created against the project item relating to the timesheet activity.
- If you have set your projects to use Overhead Absorption in the Project Accounting settings, the amount posted may be subject to an overhead recovery uplift.
- If you have set your projects to use committed costs in the Project Accounting settings and a commitment has been created for this transaction, then this will be reversed and an actual entry will be created.
Open: Project Accounting > Utilities > System Setup > Timesheet and Expense claim settings | Project Accounting
- Select to Post timesheets to Project Accounting.
- Choose whether to post manually or automatically.
To manually post timesheets to Project Accounting
Open: Project Accounting > Utilities > Import and Export > Post Timesheets to Projects.
- To filter the timesheets displayed:
- To display timesheets for a particular individual, select Show timesheets for resource and select the resource.
- To display timesheets from all resources, select Show timesheets for all resources.
- To display timesheets by date, select Range of timesheets and the week to display, then click Display.
- To display timesheets for a particular project, select Show timesheets for project and select the project.
To display timesheets from all projects, select Show timesheets for all projects.
Note: You can also sort the timesheet entries in the list by clicking on the column headings, e.g. clicking on Date will sort the list in ascending or descending date order.
-
Select the timesheets to post to Project Accounting.
Tip: To select multiple items, use the Ctrl key to pick individual items, or hold down the Shift key to select a block of items.
- To post the selected timesheets, click Post.