Amending multi item estimates
You can amend groups of estimates Forecast project costs, based on expected costs of labour, machinery and operation times. In Manufacturing, estimates are produced for one-off items or non-repetitive batches. if they were created as multi item estimates.
To amend multi item estimates
Open: Estimating > Records > Amend Multi Item Estimate.
- Select the estimate number required from the Estimate No. drop-down list. The estimates for the multi item group are listed in the estimate grid.
- Make any changes required to the estimate header details. In the estimate grid, perform the following actions for each estimate that you want to amend.
- Select the check box of the Estimate No. you want to amend.
- Estimates with a status of Entered.
- Estimates with a status of Production.
- Estimates which have been converted to works orders if the Estimates can be changed after creation of Works Order setting is selected in the Estimate Settings General tab.
- Cancelled estimates.
- The estimate, customer or product once a sales order has been created from the estimate.
- Click Edit. The Estimate Details window appears.
- Make changes to the estimate.
- To record details of the changes, click Modification History. The Enter Modification History window appears.
- Enter the change details.
- Click OK.
- To save your changes, click Save.