Create an allocation (BOM)

Note: You can only create an allocation for an active BOM.

To create an allocation

Open: Bill of Materials > Processing > New Allocation.

    Alternatively, select New Allocation in the Bill of Materials > Allocations list.

    A unique, system-generated Allocation No is displayed. When you build from an allocation, you select by Allocation No. This number is made up from:

    user number : date (ddmmyyyy) : time (hhmmss)

  1. Enter the Allocation Details.
    • The allocation Date defaults to today's date. Change the date if required.
    • Enter a Reference for the allocation if required. This may help you to identify the allocation when you build from the allocation.
  2. Add the Bill of Materials to Allocate.

    You can do this in the following ways:

    • To delete a BOM from the list, select the Stock Code and click Delete.
    • To change the order of items in the list, select the Stock Code and click either the up or down arrows.

    • If your stock system is set to use warehouses, specify the component warehouses by clicking Warehouses and selecting the warehouses from the list.
    • Change the default allocation options, if required, by clicking Options and selecting the options from the drop-down list.

      The values for these come from the Allocation tab in BOM Settings. Any changes you make here apply in this allocation only.

    Note: To ensure end to end traceability searching, using the Traceability Enquiry window, we recommend you add only one individual BOM.

  3. Set up the values for each stock item.
    1. If version control is in use and more than one version exists, select the Version.
    2. Enter the Quantity to manufacture. This defaults to the Default build quantity value set in the Bill of Material Settings General tab.

      Note: If you enter a quantity which does not match the unit of measure The quantity in which a stock item is measured for purchase, sale or storage., the quantity is automatically adjusted to the nearest appropriate value.

  4. Run the allocations reservation process by clicking Process.

    The results are calculated and displayed in the following ways:

    • The Can be built? column displays Yes or No to indicate whether the BOMs can be built. Not Processed may be displayed if you did not select the Continue option if shortages were found.
    • The Components list displays the shortages of the components required to build the BOMs that display No in the Can be built? column.

      Quantities have been converted to stock units.

      Note: The Quantity Required value will include the scrap percentage if you have selected to calculate scrap in Allocations on the BOM Settings Scrap tab.

      Sub-assemblies are highlighted in colour (blue by default).

      Shortages are highlighted in colour (red by default).

      If the item allows negative stock levels and the options Report Shortages for Components or Report Shortages for Sub-Assemblies have not been selected, then N/A is displayed in the Shortage column for components or sub-assemblies.

      If the item is a miscellaneous stock item or a single batch item, N/A is displayed in the Shortage column.

  5. Note: If you make changes to the component list, the Can be built? value is not updated.

  6. Select Print Picking List if you want to print a picking list automatically after saving the allocation, or clear the check box if you do not want to do this.

    This check box is selected by default, if you selected Print Picking List after creation of Allocation in the BOM Settings Allocation tab.

    Note: The picking list will be consolidated or not, depending on your selection for Print Consolidated Picking List in the BOM Settings Allocation tab.

  7. Save the allocation details and reserve the stock for the BOMs.

    • If you are using batch or serial numbers for traceability or you want to amend the location of the allocation, click OK and Confirm.

      Note: The allocations that you created are saved as soon as you click OK and Confirm. You only have a choice to change what has been saved.

      You can:

      • Amend the selected bins and the quantities allocated from the bins.
      • If you are using batch or serial numbers for traceability, you can change the automatically selected numbered items for allocation.

      The Confirm Items window appears and you can make the changes you want.

    • If you do not want to amend the allocation before saving it, click OK.